|
|||||
New Zealand Engineering 1999 September Practice - Legal Project Contracts - Planning for the unplanned What if? Delays at two high profile New Zealand energy projects have highlighted the importance of project contracts. When a new project is in its formative planning stages and all participants are brimming with enthusiasm and confident that it will proceed smoothly, the possibility that something could go wrong hardly merits consideration. It is sometimes assumed that the project participants will sort things out amicably if and when a problem arises. Were that always the case, project contracts could be drafted on the back of an envelope. Unfortunately, the reality, particularly with complex projects, is that unplanned difficulties do occur and, as a result, the relationships between the participants can become severely strained. As much as thorough planning is important from an engineering perspective, so too, from a legal perspective, it is essential to plan for unwanted contingencies. Project contracts set out the relationship of the parties, their respective responsibilities and obligations and allocation of risk. When unplanned contingencies arise these contracts can be sorely tested and found wanting if not prepared carefully. What if? For participants who refuse to plan for contingencies at the outset and adopt a "shell be right" attitude, the occurrence of unplanned events can be costly and result in drawn out court disputes or arbitrations. In many cases these may have been avoided or, at least, mitigated by a relatively small amount of forethought and sound advice. Things the project contractor/engineer should think about include: What happens if the project encounters delays through the non-delivery of materials from a supplier? What if a component of the facility under construction is defective due to faulty workmanship of a sub-contractor? What if the facility, when completed did not meet the agreed performance specifications? What if completion was delayed due to some other unforeseen difficulty, such as atypical weather patterns? What if the site reports or geographical surveys were inaccurate? What if the cost estimates were grossly inaccurate? And, generally, who is responsible and to what extent in each of these circumstances? Project contracts that expressly provide for unplanned contingencies and clearly allocate risk and responsibility stand a far greater chance of achieving successful completion without undue delay or major additional cost. Liquidated
damages If the liquidated damages represent a genuine pre-estimate of the loss the owner expected to suffer as a result of the failure, the Courts will not interfere with the amount set. However, if a Court found that the LDs constituted a penalty for non-performance or were being used to force the offending party into performing the contract, they will be unenforceable. For example, LDs for delay in achieving the contracted completion date may reflect the owners finance costs. The project owner and its lenders will have assumed, and funded on the basis of, repayments from the cashflow generated by the project commencing on or by the agreed completion date. The parties may also factor in loss of profit and other costs caused by delays in the commencement of input contracts, such as take or pay obligations under contracts for the supply of fuel to the facility, or output contracts, such as power sale agreements. Balance is
essential 1. Contractors responsibilities should be clearly set out in the project
contract 2. Milestone payments 3. Cap on LDs 4. Bonus payments Benefits of
careful planning Chris Gordon is a partner in the Wellington office of law firm, Bell Gully and a member of the Construction and Energy team. |
|||||
![]() |
![]() |